Entries by Catherine Mohr

Final Rough Slab

After all the back and forth with the insulation underneath the slab, it still wasn’t clear if the insulation was going to be thin enough around the edges for the rebar to be embedded deeply enough in the concrete.  It was fine in the center, but still a little thick at the edges.  But the […]

And then it was juuust right

The next step was to put the insulation under the final portion of the slab to be poured.  The guys from Spray Foam Energy Solutions (SFES) came out to examine the site, and asked for landscaping fabric to be put down over the sand (on top of the vapor barrier that is in turn on […]

Concrete Pour #2

Yes, it has been a long time in between posts.  All the details that had to be worked out to do the partial perimeter pour paled in comparison to the back and forth to finalize the forms for this pour! The final dimensions of the wine cellar walls needed to be checked and rechecked and […]

,

Landscaping Plans!

We knew from the very beginning that we wanted to go water independent, and that we wanted to plant native California plants, and we wanted a vegetable garden, and we wanted to irrigate the fruit trees with a permitted grey water system which was filtered through a grey water wetlands, and have a stream, and […]

Ideas Become Concrete

This felt like it was a long time coming, but when the day finally arrived, it was a still a bit scary.  Concrete is, well, concrete, and rather difficult (read: expensive) to change if anything is incorrect.  In the run up to the concrete trucks actually arriving, there were enough misunderstandings, tense discussions over drawings, and […]

Earth Tubes

The house is designed to have as much passive thermal management as possible.  The massive slab you see about to be poured will be a heat sink that will minimize the temperature swings inside the house (more about that later).  The main air inlets will be through earth tubes. In the heat of the summer, […]

Two Big Mistakes

After a couple of weeks of not much happening, this was a high drama week.  The guys who were going to lay out the concrete foundation came out and spray painted where the house was going to be based on the surveyor stakes.  On our Monday meeting with the general contractor, Catherine looked at the […]

Fresh Canvas… um… again

The site this weekend… almost indistinguishable from the site a few weeks ago, except for those water tank inlets sticking up waiting to have downspouts trenched to them It was a very quiet week on the build site… too quiet After a parade of excavation equipment, excavating out large quantities of dirt, piling it up […]

Dirt, dirt, more dirt, and now…. mud

Truth shall spring from the earth….The excavation for the foundation started this week.  The first step was to break up all the remaining concrete driveway around the perimeter.  While climbing around on the pile of broken concrete, Natalie found many leaf imprints which had been made on the underside of the concrete driveway when it […]

,

Rainwater cachement

This week we put in a 9000 gallon rainwater cachement tank. It is quite a business putting in a tank this big. First, a huge hole must be dug, then the tank is brought in (random people on the street asked if it was a submarine…), a huge crane lowers the tank into the hole, […]